When you’re delivering a Salesforce project, you’re probably using a form of agile methodology. It’s the popular kid these days.
Work is usually migrated from a Development (DEV) sandbox to a Quality Assurance (QA) sandbox every two weeks. Towards the end of the sprint, you’ll probably want to demonstrate to the client what was done in that sprint.
This means a few things:
- You don’t actually have two weeks to develop and migrate. You have two weeks minus the number of days to migrate and test, and minus a day for the demo. This is an important consideration as you plan for the sprint.
- You need to test the work in QA before the demo. In addition to eating up more time, you’ll need to resolve any defects quickly.
- Documentation needs to be updated, which is easier if you’re doing something fancy with DevOps. Either way, the user story needs to be modified.
- The client will probably have feedback. Managing this feedback is another topic, but it’s important to mention it here because it will impact your next sprint.
- You need good test data. Using “Test Test” as a contact name won’t have the same impact as “John Wick” or “Luke Skywalker”. Just be sure names are appropriate.
The takeaway
Two weeks sprints are not actually two weeks; they are more like 1.5 weeks. Keep this in mind during the sprint planning.